Schedule of Proceedings Matter: 71-2023-01 Totem V CONNECT

Step Date Responses to Board Questions July 22, 2024 Totem responses to all interrogatory questions July 22, 2024 Deficiency motions, if any August 7, 2024 Replies to Responses to Board Questions August 12, 2024 Ruling on any Deficiency motions TBD Final responses to interrogatory questions September 11, 2024 CONNECT files Expert Report October 16, 2024 Totem files any response Expert Report November 15, 2024 Each Party files Final Submissions December 6, 2024 Each Party files their Reply to Final December 20, 2024 Submissions