[CB-CDA 2024-080]
RULING OF THE BOARD
Proceeding: 71-2023-01 Totem Médias Inc. v CONNECT Music Licensing Service Inc.
October 16, 2024
One week delay is granted
[1] On October 15, 2024, CONNECT requested a one-week extension to file an Expert Report. CONNECT did not provide a reason for the request.
[2] Given that CONNECT has not requested many delays in this proceeding, and given that this is a s. 71 proceeding not directly affecting non-parties, I grant the request.
New Schedule
[3] The Schedule of Proceedings is now as follows:
Step
|
Date
|
CONNECT files Expert Report |
October 23, 2024 |
Totem files any Responding Expert Report |
November 22, 2024 |
Each Party files Final Submissions |
December 13, 2024 |
Each Party files their Reply to Final Submissions |
January 8, 2025 |
[4] If Totem does not intend to file a Responding Expert Report, it is asked to please inform me of this. I will adjust the dates of this Schedule accordingly.
Luc Martineau
Case Manager